Equipment for a processing line for gold-bearing ore was supplied, including the delivery of geomaterials for heap leaching site preparation. Shipments to Port Sudan were made from the ports of St. Petersburg, Riga, Novorossiysk, Klaipeda, and Valencia.
The work was carried out in several stages:
1. Heap leaching site preparation - laying geotextile, laying and welding geomembrane.
2. Assembly and installation of crushing and sorting complex equipment, electrical work.
3. Commissioning work and bringing the complex to the declared productivity.