From February 25 to April 7, 2021, the installation and commissioning of the crushing and sorting complex in the Sverdlovsk region were carried out. The project was completed "turnkey": assembly, electrical installation (cable pulling, wiring, installation of control cabinets, cable entry into the control room), commissioning and start-up of the complex with protection of qualitative and quantitative characteristics. All work was completed on time, despite difficult weather conditions. After load testing for three shifts, the customer team was successfully trained and the crushing and sorting complex was launched in "combat" mode.